Concept 1 of 61 min
How project finance is structured
Gearing a project
| Project cost | 500 |
|---|---|
| Gearing | 80% |
- Debt = 500 × 80% = 400
- Equity = 500 − 400 = 100
The debt is non-recourse: lenders look only to the project's cash flows.
Liquidated damages
| Days late | 60 |
|---|---|
| Damages a day | 0.2 |
- Paid by the contractor = 60 × 0.2 = 12
The damages cover lost revenue and debt service during the delay.
- ConstructionThe riskiest phase, under a fixed-price EPC contract
- Ramp-upFirst revenues, still uncertain
- OperationsA track record, so lower required returns
Gearing is often 70% to 90% debt for contracted assets. Construction risk passes to the builder under a fixed-price EPC (engineering, procurement and construction) contract.
Ring-fencing the project lets sponsors borrow against cash flows they do not guarantee; lenders look at the contracts and the cash, not at the sponsors' balance sheets.
Stable contracted revenue supports high leverage; projects with demand or merchant risk carry less. Construction is the riskiest phase: a lump-sum turnkey engineering, procurement and construction (EPC) contract makes the builder bear cost overruns and delays, backed by liquidated damages, often a daily amount up to a cap, and by bonds.
A greenfield project still has to be built and ramp up, so it needs higher returns than a brownfield asset with a track record.
- Thinking the sponsors guarantee the debt.
- Leaving construction risk with the lenders or the public authority.
- Confusing greenfield with unused land.
Why are large infrastructure projects financed off the sponsors' balance sheets?
A complete answer covers
- An SPV borrows against the project's own contracts and cash flows, without recourse.
- Sponsors limit their risk to the equity they put in.
- Contracted cash flows support high gearing, often 70% to 90%.
- Risks are passed to whoever controls them: construction to the EPC contractor, for instance.
Also in our technical interviews, on camera, with a score.
Concept 2 of 61 min
Sizing debt on the DSCR
The why, the charts, the worked example and the interview questions are in Essentials, with every quiz.
See the plansSign inConcept 3 of 61 min
What protects project lenders
The why, the charts, the worked example and the interview questions are in Essentials, with every quiz.
See the plansSign inConcept 4 of 61 min
Concessions and PPPs
The why, the charts, the worked example and the interview questions are in Essentials, with every quiz.
See the plansSign inConcept 5 of 61 min
Infrastructure equity returns
The why, the charts, the worked example and the interview questions are in Essentials, with every quiz.
See the plansSign inConcept 6 of 61 min
AdvancedTwo tests size the debt: which one binds
The why, the charts, the worked example and the interview questions are in Essentials, with every quiz.
See the plansSign inRecap
- Project finance is non-recourse: an SPV borrows 70% to 90% of the cost against the project's own contracts and cash flows.
- DSCR = CFADS ÷ debt service; maximum debt service = CFADS ÷ minimum DSCR; the debt it supports is its present value.
- Lenders protect themselves with a minimum DSCR, a lock-up before default, a reserve account, hedging and a tail before the concession ends.
- A concession has no terminal value: its cash flows stop at hand-back; availability payments remove traffic risk, tolls keep it.
- Contracted, often indexed cash flows justify lower equity returns; fixed-rate debt against indexed revenue makes equity an inflation hedge.
25 questions on Infrastructure and project finance
Timed, like the real one, drawn from a bank of 33. Every answer explained.