Concept 1 of 71 min
Variances, flexed budgets and bridges
Volume and price variances
| Budget | 2,000 units at 15 |
|---|---|
| Actual | 1,800 units at 16 |
- Budget revenue = 2,000 × 15 = 30,000
- Actual revenue = 1,800 × 16 = 28,800
- Volume variance = (1,800 − 2,000) × 15 = −3,000
- Price variance = (16 − 15) × 1,800 = +1,800
- Total = −3,000 + 1,800 = −1,200
The 2 variances explain the whole gap between 28,800 and 30,000.
Costs are judged against a budget flexed to actual volume. A shift to lower-margin products lowers the margin at flat volume.
A bridge walks from last year to this year through volume, price, mix, costs and FX (foreign exchange). Using budget units for the price effect leaves a gap that the 2 variances no longer explain.
Comparing costs with the original budget mixes the volume effect with cost control. Revenue growth can hide a margin squeeze, which is why bridges split volume, price and mix.
A volume variance values the units missed or gained at the budget price, a price variance values the price change on the units actually sold, so together they add up exactly to the revenue gap. A bridge is how management and investors read performance.
- Using budget units for the price variance.
- Judging costs against the unflexed budget.
- Reading revenue growth as profit growth.
Sales beat budget by 8% but operating profit missed. Walk me through how you would explain it to the CFO.
A complete answer covers
- Build a bridge from budget to actual profit.
- Split revenue into volume, price and mix effects.
- Flex costs to actual volume, then show true cost overruns.
- Isolate currency and one-offs, and say what is recurring.
Also in our technical interviews, on camera, with a score.
Concept 2 of 71 min
Fixed and variable costs, break-even and allocations
The why, the charts, the worked example and the interview questions are in Essentials, with every quiz.
See the plansSign inConcept 3 of 71 min
Budgets and forecasts that work
The why, the charts, the worked example and the interview questions are in Essentials, with every quiz.
See the plansSign inConcept 4 of 71 min
Headcount costs and margin targets
The why, the charts, the worked example and the interview questions are in Essentials, with every quiz.
See the plansSign inConcept 5 of 71 min
Organic growth, working capital and cash
The why, the charts, the worked example and the interview questions are in Essentials, with every quiz.
See the plansSign inConcept 6 of 71 min
Sensitivities, scenarios and leading indicators
The why, the charts, the worked example and the interview questions are in Essentials, with every quiz.
See the plansSign inConcept 7 of 71 min
AdvancedMore units, less margin: the mix effect
The why, the charts, the worked example and the interview questions are in Essentials, with every quiz.
See the plansSign inRecap
- Volume variance = change in units × budget price; price variance = actual units × change in price; flex costs to actual volume before judging them.
- Break-even units = fixed costs ÷ contribution per unit; break-even revenue = fixed costs ÷ contribution margin.
- Rolling, driver-based forecasts beat static, top-down budgets; budgets beaten every year hide slack.
- Headcount costs include on-costs and start dates; targets apply to next year's revenue.
- Organic growth strips out acquisitions and currency; cash differs from profit through working capital, capex and debt.
25 questions on FP&A and controlling
Timed, like the real one, drawn from a bank of 33. Every answer explained.